Rough-Cut Capacity Planning By Using the Overall Planning Factors Method: An Applied Study in the Leather Clothes Factory / Textile and Leather Industries Company

  • Zahra Abd Mohammed
Palabras clave: Master Production Scheduling, Capacity, Capacity Planning, Rough-Cut Capacity Planning, Overall Planning Factors

Resumen

Most Iraqi industrial companies and factories suffer from a weakness in the capacity planning process because of their lack of reliance on scientific foun- dations in the rough-cut capacity planning process. One of those methods is the overall planning factors method. The research problem focused on ex- plaining how overall Planning factors are used in the rough-cut capacity plan- ning; therefore, the aim of the research is to apply the overall factors in the rough-cut capacity planning through preparing logical steps for the rough-cut capacity planning process by using overall Planning factors. To implement the steps, the mathematical equations have been formulated so that the steps and equations can be used usefully in many industrial companies, and determined the capacity needs for both direct labor time, machine time and for each type of product and the time periods that are specified, as well as determined the capacity needs of each of the work centers. For the purpose of applying the research, the leather garment factory affiliated to the Textile and Leather In- dustries Company was chosen which produces four types of leather garment (men’s jacket, men’s vest, women’s jacket, and women’s coat). The researcher conducted many field visits and interviews to obtain the main data of sched- uling the production as well as historical data related to production quantities and times related to the direct labor and machine and for each type of product. The research concluded that the management of the leather garment factory is not accomplishing the preparation of the master production scheduling accu- rately, and also not using any scientific method in the rough-cut capacity plan- ning. The research also concluded that the process of manufacturing leather garment depends on the direct labor times, which ratio reached to (0.69), while the machine times reached (0.31). Therefore, the research recom- mends for preparing the master production scheduling accurately, as well as relying on the overall Planning factors in the rough-cut capacity plan- ning, and finally the use of the tailor-made machines in the tailor-made center which will help reducing the required time to implement the tai- lor-made process and thus it reduces the manufacturing time.

Biografía del autor/a

Zahra Abd Mohammed
Mustansiriyah University/College of Administration and Economics Department of Business Administration/ Baghdad-Iraq

Citas

Benton, W. C. (2014), Supply Chain Focused Manufacturing Planning and Control, Cengage Learning, U.S.A.

Das, A. (2016), An international to Operations Management, 1st edition Routledge Taylor &Francis Group, New York.

Davis, M., Aquilano, N. J., and Chase, R. B.,(2003), Fundamentals of Operations Management, 4th ed., McGraw – Hill Irwin, New York.

Dilworth, J. B.,(2000), Operations Management: Providing Value in Goods and Services, 3rd ed., Harcourt, Inc., College Publishers, New York. 5. Gaither, N and Frazier, G, (2002), Operations Management, 9th ed., South – Western Thomson, U.S.A.

Groover, M.P (2010), Fundamentals of Modern Manufacturing: Materials, Processes, and Systems, 4th ed, John Wiley & Sons, Inc., U.S.A.

Jonsson, P. and Mattsson, S.A. (2002), “The Use and Applicability of Capacity Planning Methods”, Production and Inventory Management Journal, Vol. 43, No. 3/4, pp: 89-95.

Krajewski, L.J., Malhotra, M.K and Ritzman ,L.P., (2016), Operations Management: Process and Supply Chains, 11th ed, Global edition, Pear- son, Boston, U.S.A.

Kumar,S.A., and Suresh,N., (2009), Operations Management, New Age International (P) Limited Publishers, New Delhi, India.

Leseure, M.,(2010), Key Concepts in Operations Management, 1st edition, SAGE Publications Ltd, London.

Radhika , S., Rao, S., and Pavan, K, (2013), “A Differential Evolution based Optimization for Master Production Scheduling Problems”, Inter- national Journal of Hybrid Information Technology, Vol.6, No.5, pp:163- 170.

Reid, R.D., and Sanders, N. R. (2011), Operations Management, 4th edition, John Wiley & Sons, Ins. U.S.A.

Reid, R. D., and Sanders, N. R. (2013), Operations Management: An Integrated Approach , 5th edition, John Wiley & Sons, Ins. U.S.A.

Russell, R., and Taylor, B. W., (2011), Operations Management- Cre- ating Value along the Supply Chain, 7th edition, John Wiley & Sons, Inc., U.S.A.

Schroeder, R, G & Goldstein, S.M., (2018), Operations Management in the Supply Chain: Decisions and Cases, 7th edition, McGraw-Hill Edu- cation, 2 Penn Plaza, New York.

Slack, N., and Lewis M., (2017), Operations Strategy, 4th edition, Pearson education limited, England.

Smunt, T.L, (1996), “Rough Cut Capacity Planning in a Learning Environment” IEEE Transactions on Engineering Management, Vol. 43, No.3, pp: 334-341

Stevenson, W. J., (2018), Operations Management, 13th edition, McGraw-Hill Education, New York.

White, G. p and Vonderembse, M. A.,(1991) , Operations Management: Concepts, Methods, and Strategies, West Publishing Company, New York.

Publicado
2019-08-13
Cómo citar
Abd Mohammed, Z. (2019). Rough-Cut Capacity Planning By Using the Overall Planning Factors Method: An Applied Study in the Leather Clothes Factory / Textile and Leather Industries Company. Opción, 35, 908-931. Recuperado a partir de https://produccioncientificaluz.org/index.php/opcion/article/view/31659